I am ready meet challenges the jobs demand. I am promising to work enthusiasm and zeal to give the utmost satisfaction.
Overview
9
9
years of professional experience
1
1
Certification
Work History
Electrical project engineer
MONENCO CONSULTING ENGINEERS
06.2024 - Current
Participates in the preparation of project planning, scope of work for tendering, evaluation, project implementation, expansion, integration, and modification and acceptance tests of power plants equipment
Assist Team leader in preparing annual budget and specification of spares to be purchase for maintenance requirements and stocks of power plant equipment
Provide Daily –monthly network status reports
Co-Ordination during system replacement/upgrades with the vendor and other departments
Provide input into strategies, objectives and activities for the team
Ensure that Preventative Maintenance routines are followed to maximize network availability of Rectifiers, Inverters, Batteries, Diesel Generator Sets, Automatic Mains Failure Panels and their associated electrical systems
Participate in new project implementations, installation, testing of Power equipment, DC cabling and other projects
Co-Ordination during system replacement/upgrades with the vendor and other departments
Provide input into strategies, objectives and activities for the team
Analyses data, prepares statistics and suggests recommendations
Performs all coordination, supervision and monitoring to External maintenance contractor
Provide technical support for higher level / complex faults or problems
Fault analysis and do corrective maintenance routines to control them
Imparts on- the- job training to the newly recruited staff in the team
Close monitoring of contractual companies in relation to the Team
All External & internal Customer
Check and review the contractors’ invoices for each individual project
Review of the electrical document’s specifications e.g
Drawings, to ensure the electrical specification is in line with requirements
Visits sites to monitor progress and the installation of all electrical equipment
Reports all findings and raises discrepancies where necessary
Ensuring that all projects are of the highest quality in line with electrical quality standards and that the relevant technical knowledge is included into all aspects of the job
Meter supervisor
ALPHA ELECTRICAL & CONTRACTOR
03.2021 - 05.2024
Handle metering project right from tendering stage till successful handing over
Hands on knowledge on latest wired and wireless communication technologies, metering standards, testing procedures etc., also capable of gathering requirements, finalizing and assisting software team in Energy accounting, auditing, online monitoring and billing software
Responsibilities: Site in Charge
Coordinated with NDS staff and third-party contractor, conduct field survey and install smart meters & communication modules
Coordinate with NDS O&M Team and arranging the shutdown plan for testing
Integrating installed meters with server and prepare the report for commissioning
Software inputs prepared based on Technical Specification
Web based application tested as per requirement
Generate reports based on utility requirements
Inspect all the PSS and GRID Substation and conduct the injection test for all33KV and11 KV Tariff energy meters
Preparing the Test reports as per NDS requirement
The configuration of CRT Meters, AMR Meters and CTVT Meters as per NDS requirements
Monitor the HES and MDM AMR system on Daily basics and check the Meter communication performances
Monitor all the AMR Meter event logs from HES system on daily basics, in case of found any tampering related events
Take the necessary actions to rectify the issues
Monitor the AMR Communication of all the CRT AMR meters on daily basics, If Case of any meter faulty or communication failures must take immediate actions
Analyze the monthly consumptions for all the CRT meters, In case of any drop or deviations found in the actual consumptions same need to be inspected
Energy Theft Detection:
Monitor all the AMR Meter event logs from HES system on daily basics, in case of found any tampering related events
Take the necessary actions to rectify the issues
Monitor the Power quality events from HES system on daily basics, in case of found any failure in the Voltage or current same to be informed with concern team and take necessary actions to solve the issues
Bad data detections:
Check all the AMR connected Meters are correctly mapped with proper Legacy customer account numbers with HES and MDM
Check all the AMR high value CT and CT VT AMR meters are configured with connected CT and VT ratios
False data injection -In case of found any mismatch record in the Meter serial number, IP address or CT ratios same to be corrected
Check all the Metering Parameters with AMR system in case of found any abnormal recording same to be informed to Meter Manufacturer or suppliers
Site engineer
ALTASNIM ENTERPRISES
01.2018 - 01.2021
Installation, testing & commissioning of MV/LV substations and associated downstream distribution, bus duct
Earthing, cable management system, Glanding /termination, C&I Cable management system
Responsibilities: Site in Charge
Site Management-all correspondences & meeting with client Preparation of Project schedules & shop drawings
Site engineer
SEPCO III
01.2016 - 01.2017
Installation, testing & commissioning of LV and associated downstream distribution, bus duct
Earthing, wiring management system
Responsibilities: Site in Charge
Site Management-all correspondences & meeting with client Preparation of Project schedules & shop drawings